Location: Cleveland, OH | Industry: Education

Our team provided Construction Management services during Pre-construction to the CIA as part of a campus-wide improvement planning effort (44,196 SF renovation, 82,804 SF new construction). During construction, we provided representation on site including site observations/reporting, cost control, schedule review / analysis, pay application review and coordination with internal CIA personnel and adjacent property owners / tenants. We were heavily involved in VE and cost estimating during the Design Phase to enable the project to be funded, and allowing it to move forward into construction. We worked with the Project design team and CIA personnel to reduce the project costs by $10 Million.
Construction Cost
$22.5 Million